Friday, 17 January 2014

Environmental Impact Assessment


Environmental Impact Assessment(EIA)


  1.             Key Elements of an Initial Project Description and Scoping

 The key environmental issues to be considered in relation to a projects characteristics are discussed in Sectoral Guidelines published by MoEF from time to time. An Initial Project Description (IPD) should at the very least provide the reviewer with all the information necessary to enable project screening and scoping.
 Specific information that must be covered by the IPD includes:


  1.    Location/current land use along with contours and whether it conforms to the development plans proposed for that area.
  2.       Details of proposed project activity including the project cost.
  3.    Outlining the key project elements during the pre-construction, the construction and the operation phases etc. as per the list of documents to be attached with the questionnaire
  4.      The IPD may also include.
                         - Off-site activities
                         - Associated activities
                         - Expected project induced activities
                        - Project activities as PERT chart and process as a flow chart delineating unit processes with input-output.
                The project proponent after suitable scoping should  provide environmental information for consideration in detailed EIA. The reviewer while assessing  the report should focus on the crucial aspects involving project location and characteristics.

Project Location(s)
The site(s) selection can be an effective approach in minimising the requirement of mitigation measures. Proposed project locations should be reviewed based upon regulatory and non-regulatory criteria. Project siting restrictions depend on the sensitivity of the surrounding environment. Sensitivity should be assessed in relation to proximity of the project to the  places/sites listed in list of identified ecologically sensitive zones (ESZ) notified by MOEF.
 The siting criteria delineated by MoEF include:

  1.  As far as possible prime agricultural land/forest land may not be converted into an industrial site.
  2. Land acquired should be minimum but sufficient to provide for a green belt wherein the treated wastewater, if possible/suitable, could be utilised from wastewater treatment systems.
  3. Enough space may be provided for storing solid wastes. The space and the waste can be  made available for possible reuse in future.
  4. Layout and form of the project must conform to the landscape of the area without unduly affecting the scenic features of that place.
  5.  Associated township of the project if any to be created must provide for space for photo-graphic barrier between the project and the township and should take into account predominant wind direction.

 In addition the following distances should be maintained:

  1.     Coastal Areas: at least 1/2 km from the high tide line (within 0.5 km of High Tide Line  (HTL), specified activities as per CRZ notification, 1991 are permitted)(The HTL is to be delineated by the authorised agency only.)
  2.         Estuaries: At least 200 metres from the estuary boundaries
  3.       Flood Plains of the Riverine systems: at least 500 metres from flood plain or modified  flood plain or by flood control systems
  4.       Transport/Communication System: at least 500 metres from highway and railway
  5.       Major Settlements (3,00,000 population) at least 25 km from the projected growth  boundary of the settlement

 In addition to the siting criteria listed above, the proposed project location should be reviewed in  relation to the following salient issues:

  1. Ambient air, water and noise quality standards
  2. Critically polluted areas
  3. Natural disaster prone areas
  4. Ecologically sensitive areas
  5. Availability of water and other critical infrastructures like electricity, roads with adequate  width and capacity 

 Land Use Impacts

When assessing the significance of potential land use impacts, the reviewer will need to consider
the following:

  1.          Total land coverage of the project
  2.          Expected change in the landscape and topography
  3.          Present and designated land use in conformity with regional developmental plans / master  plan
  4.          Dependent/resident population
  5.          Assessed land capability/suitability in the region
  6.         Assessed erosion potential in the region
  7.         Unstable or critical hydrologic, biotic and abiotic components systems (especially drainage)
  8.         Slope stability and proneness to land slide hazards
  9.         Designated land use in the master plan/regional development plan

Consideration of Alternatives

 Alternatives must be considered with respect to the following:

  1.         No project
  2.        Siting of the project
  3.        Technology/Processes

 The reviewer will need to evaluate whether or not the proposal has taken into  consideration all feasible alternatives in respect of siting, and the plant processes including mitigation methods.

 No project:
 Alternatives of no project situation need to be weighed against the ecological implications.

 Siting of the project:
 Specific information that must be covered in site selection should include:

  1.         Status of conformance with siting guidelines of MoEF
  2.         Ambient environmental quality in the region and conformance
  3.         Existence of sensitive receptors in the impact zone
  4.         The characteristics of soil strata and potential for groundwater depletion/ contamination
  5.         The location of the site in relation to the watershed, and suitability of the site vegetation  and ecology
  6.         Extent of resettlement and rehabilitation, including vulnerability of the affected populations
  7.         Likely Stress on public utilities and services in the region
  8.         Likely Stress on the ecosystem

 Process selection:
 Criteria for the process selection should include:

  1.         Choices of inputs to generate minimal wastes and emissions causing minimum stress on  resources
  2.         Pollution prevention through maximising efficiency in the utilization of inputs
  3.         Recycling and reuse of wastes and emissions
  4.         Treatment of wastes and emissions
  5.         Choice of appropriate mitigation methods to reduce the impacts

 Construction Phase
 Project construction may require cutting, striping, levelling landscaping, topographic, sea / riverbed or subsurface transformations, opening of new quarries transportation of men and materials, construction of temporary houses any of which can cause both positive and negative environmental impacts.

 The construction phase is especially significant in the case of infrastructure projects. In such cases a detailed schedule of construction activities is critical for scoping impacts. If the construction stretches over a prolonged period (1-3 years), the impacts of habitat disturbances may be even more severe in the construction phase than during operation phase. In addition, there may be substantial influx of labour in some project areas that could create stress on public utilities, services, public health and social relations.

 Input Requirements
 A pre-requisite to estimating the potential environmental impacts of a project is the identification  and recording of the total project inputs including process technology, raw materials, water and energy.
 While not exhaustive, below is a checklist of the information likely to be required  for the scoping of project inputs.

Information required:

Project Technology

  1.         Available technology/equipment
  2.         Cleaner options

 Land

  1.         Nature of land/soil
  2.         Topography

 Materials

  1.         Physical and chemical nature of raw materials
  2.         Source of raw material
  3.         Storage
  4.         Precautionary measures
  5.         Mine discharge
  6.         Top soil preservation and reuse
  7.         Project output

Hazardous/Toxic materials management
1.   Requirements of processing, transportation and handling of any hazardous/toxic /flammable/explosive material(s)
2.   Storage requirement for hazardous/toxic flammable / explosive material(s)
3.   Usage of any recycled, salvaged material from industrial waste in the process.

Water
 Water requirement

  1.         Average demand, peak demand at full production, source and type (treated/ untreated)
  2.         Water drawal at intake vis-vis the requirement of competing user (If water supply is to be augmented from other source(s) for meeting both present and  future requirements)
  3.         Physico-Chemical characteristics of surface/ground water at the site and likely impact area
  4.         Treatment requirements of water before use
  5.         Physico-Chemical characteristics of treated water
 Energy/Fuel
 Total power requirement for

  1.         Existing facilities
  2.        Proposed facilities
 Sources of power supply

  1.         Public supply
  2.        D.G.Set/Gas turbine
  3.         Captive power plant
  4.        Capacity, type of fuel, consumption
 Details of fuel used

  1.         Coal
  2.        Natural gas
  3.         LSHS
  4.        HSD
  5.        Naphtha
  6.          Furnace Oil
  7.         Other (specify)
  8.       Consumption (tonnes/day), Calorific Value (K Joules, kg), % Ash, % Sulphur,  Source of supply, Mode of transportation to the plant site with justification and  linkage details of technology for power generation
 Transport

  1.         Details of transport system to be used for transporting raw materials, finished products and  wastes

 Wastes and Emissions
 An assessment of the significant environmental issues for each phase of the project in relation to wastes and emissions involve

  1.         Potential releases
  2.         The receiving environment including bio-environment
  
 The issues that need to be identified are

  1.         Air emissions
  2.         Noise
  3.         Liquid effluents
  4.         Solid wastes
  5.         Hazardous/Toxic Wastes
Types of release and potential sources. 

A.      Air Emissions
a.       Emissions from Compaction & setting during construction
b.      Emissions from Drilling & blasting
c.       Emissions from Operation of DG. Sets/captive power plant
d.      Vehicular emissions
e.      Emissions from storages & transport
f.        Process emissions
g.       Fugitive emissions
h.      Accidental /emergency releases
i.         Emissions from Fuel combustion
j.        Offsite emissions

B.      Noise & Vibrations
a.       Generated by the plant and equipment
b.      From Vehicles
c.       Blast induced ground vibrations


C.      Liquid Effluents
a.       Process and domestic effluents
b.      Offsite effluents
c.       Storm water
d.      Cooling tower effluents and boiler blow downs
e.      Effluents from treatment plant
f.        Effluents from emission mitigation system
g.       Acid Drainage
h.      Tailing Residue emplacement
i.         Ground / surface water contamination
j.        Accidental / emergency & spills
       D.  Solid Waste
a.       Domestic solid waste
b.      Soil overburden/Dredged material/stripping and quarrying waste
c.       Process/storage units sludge
d.      Sludge form ETP/STP
e.      Waste from emission mitigation system
f.        Accidental / emergency dumps
E.      Hazardous / Toxic Waste
a.       Process / Storage units (tank bottoms)
b.      Sludge form Waste water treatment
c.       Sludge form Emission treatment system
d.      Leachates from storage
e.      Genetically modified organisms
f.        Biotechnological activities and related emissions and wastes

 Air Emissions
The issues for air emissions should be based on project location (valley, coastal areas, regions  with frequent dust storms etc.) type of activity and air polluting potential. A list  of key activities and associated air pollutants are listed.

 Liquid Effluents
Detailed assessment will be required where: 

  1.         The proposed receiving body is surface water, irrigation canal, marine coast, public sewers  etc.
  2.         The discharge point is within the catchment area of a drinking water source or a river stretch designated for drinking purposes (as per CPCB designated usages)
  3.     The disposal is on land, the soil is permeable and the aquifer conditions are prone to  groundwater contamination

 Solid Wastes
  Solid waste can be toxic or non-toxic. A list of toxic or hazardous waste classifications can be found in the MOEFs Hazardous Waste - Management and Handling Rules, Manufacture, Storage and Import of Hazardous Chemicals, genetically modified organisms/biotechnology activities and related emissions and wastes and related amendments notified from time to time. Where a project proposal includes any of the waste classes or activities listed in these documents the proposal should identify this and meet their requirements.

 Should the proponent be unable to confirm the existence of an acceptable treatment or disposal facility for any of the listed hazardous wastes classes with adequate capacity the issue will need to form input into the detailed assessment. It is important to note that in addition to those wastes that are classified, all potential waste groups should be examined according to the following parameters:


  1.          Moisture and High Volatile matter
  2.         Oil and Grease
  3.         Calorific value
  4.         pH
  5.        Conductivity
  6.         Heavy metal (Cr, Pb, Cu, Mn, Zn, Ni) concentrations
  7.         Phenolic compound concentration

The comprehensive inventorization of solid wastes is necessary, if

  1.        The region has no land for disposal
  2.        Existing capacity of the dumping site is near exhaustion
  3.     The region has high intensity and/or duration of rainfall and the region is prone to  flooding/water logging/high ground water table.
Risks to Environment and Human Health
Impacts to environment and human health can occur from accidents (both on-site and off-site) or  through general environmental degradation. When determining the appropriate areas for a more  detailed risk assessment, the reviewer should take into account both the type of risks inherent in a  particular activity and the potential for human/ environment exposure.

Onsite
 Exposure to fugitive dust, noise, gases, thermal and other emissions

  1.         House keeping practices requiring contact with solid and liquid toxic wastes
  2.        Emission/spillage etc. from storage & handling
  3.         Exposure to explosive material
  4.        Exposure to toxic chemicals

 Offsite
 Exposure to toxic releases from offsite / storage/related activities

  1.         Contamination of ground / drinking water due to accidental releases or normal  release in combination with natural hazard
  2.         Deposition of toxic pollutants in vegetation / other sinks and possible sudden releases due to accidental occurrences
Socio-Economic Impacts
It is generally envisaged that the scale of a projects socio-economic impact study is limited to  the region and population directly influenced by the project, with an emphasis on the distribution of benefits and costs among the project stakeholders. Within project scoping, the socio-economic issues should be addressed as below:

Socio-economic

  1.      Onsite and offsite optimal land requirements, specifically in relation to the potential  for displacement, rehabilitation, and habitat fragmentation
  2.         Land acquisition details
  3.        Quantity and nature of employment and /or estimated needs for migratory workers
  4.         Potential for stress/ increase on utilities and services
  5.         Potential benefits/disbenefits to the local habitants resulting through project and ancillary activities
  6.         Impact on health of/due to migrant labour
  7.         Impact on education of male/female
  8.         Community health impacts
  9.           Potential impacts on existing occupations and economic activities
  10.          Potential losses of livelihood for local and vulnerable sections of the population
  11.         Stress on medicinal plants
  12.           Potential impacts to archaeological monuments and culturally/religiously important locations

Ecological Impacts
 Project proposals located nearby wildlife sanctuaries, National Parks, and/or biosphere reserves,  breeding /spawning /nesting grounds etc need to come under careful scrutiny, and the  EIA report should contain impact on such ecologically fragile/sensitive areas.

Global Environmental Issues
 India is a signatory to many international agreements ratifying her commitment to environmental concerns. Therefore global concerns must also be considered. The reviewer will need to note whether a projects potential resource consumption, waste generation and emissions could break international codes of practice and where this is the case, the proponent should identify, evaluate and suggest mitigation measures if any in the EIA report.
 There are a number of additional/optional areas, which may be considered:

  1.          Potential trans. - boundary transport of atmospheric pollutants or liquid effluents.
  2.         Potential impacts to wetlands of international importance and those that attract migratory birds
  3.         The use or production of hazardous or toxic materials
  4.      Potential impacts on primitive and rare cultivated plants, land, ethnic minorities, and archaeological places
  5.         Impacts on identified rare and endangered species.
            Emissions of nuclear radiation on-site and off-site and potential for nuclear accidents 

Tuesday, 7 January 2014

Environmental Impact Assessment

Environmental Impact Assessment(EIA)


             Environmental impact assessment (EIA) is one of the tools available with the planners to harmonise development activities with the environmental concerns.

The objective of EIA is to foresee the potential environmental problems that would arise out of a proposed development and address them in the project's planning and design stage. The EIA process should then allow for the communication of this information to:

(a) the project proponent;
(b) the regulatory agencies; and,
(c) all stakeholders and interest groups.


EIA integrates the environmental concerns in the developmental activities right at the time of initiating for preparing the feasibility report. In doing so it can enable the integration of environmental concerns and mitigation measures in project development. EIA can often prevent future liabilities or expensive alterations in project design.

The EIA Cycle and Procedures

The EIA process in India is made up of the following phases:

1.       Screening
2.       Scoping and consideration of alternatives
3.       Baseline data collection
4.       Impact prediction
5.       Assessment of alternatives, delineation of mitigation measures and environmental impact statement.
6.       Public hearing
7.       Environment Management Plan
8.       Decision making
9.       Monitoring the clearance conditions

Screening
Screening is done to see whether a project requires environmental clearance as per the statutory notifications. Screening Criteria are based upon: 
  • Scales of investment
  • Type of development
  • Location of development.
      Scoping 
Scoping is a process of detailing the terms of reference of EIA. It has to be done by the consultant in consultation with the project proponent and guidance, if need be, from Impact Assessment Agency
  

      Baseline Data 
      Baseline data describes the existing environmental status of the identified study area. The site-specific primary data should be monitored for the identified parameters and supplemented by secondary data if available.
     
        Impact Prediction 

      Impact prediction is a way of mapping the environmental consequences of the significant aspects of the project and its alternatives. Environmental impact can never be predicted with absolute certainty and this is all the more reason to consider all possible factors and take all possible precautions for reducing the degree of uncertainty.

          The following impacts of the project should be assessed:

            1.Air
a. Changes in ambient levels and ground level concentrations due to total emissions from point, line and area sources
b. Effects on soils, materials, vegetation, and human health
            2.Noise
a. Changes in ambient levels due to noise generated from equipment and movement of vehicles
b. Effect on fauna and human health
            3.Water
a. Availability to competing users
b. Changes in quality
c. Sediment transport
d. Ingress of saline water
            4.Land
a. Changes in land use and drainage pattern
b. Changes in land quality including effects of waste disposal
c. Changes in shoreline/riverbank and their stability
            5.Biological
a. Deforestation/tree-cutting and shrinkage of animal habitat.
b. Impact on fauna and flora (including aquatic species if any) due to contaminants/pollutants
c. Impact on rare and endangered species, endemic species, and migratory path/route of animals.
d. Impact on breeding and nesting grounds

             6.Socio-Economic
a. Impact on the local community including demographic changes.
b. Impact on economic status
c. Impact on human health.
d. Iimpact of increased traffic

Assessment of Alternatives, Delineation of Mitigation Measures and Environmental Impact  Assessment Report

For every project, possible alternatives should be identified and environmental attributes compared. Alternatives should cover both project location and process technologies. Alternatives should consider no project option also. Alternatives should then be ranked for selection of the best environmental option for optimum economic benefits to the community at large.

 Once alternatives have been reviewed, a mitigation plan should be drawn up for the selected option and is supplemented with an Environmental Management Plan (EMP) to guide the proponent towards environmental improvements. The EMP is a crucial input to monitoring the clearance conditions and therefore details of monitoring should be included in the EMP.

An EIA report should provide clear information to the decision-maker on the different environmental scenarios without the project, with the project and with project alternatives. Uncertainties should be clearly reflected in the EIA report.

Public Hearing

Law requires that the public must be informed and consulted on a proposed development after the completion of EIA report.

Any one likely to be affected by the proposed project is entitled to have access to the Executive Summary of the EIA. The affected persons may include:

          1.       Bonafide local residents;
          2.       Local associations;
          3.       Environmental groups: active in the area
          4.       Any other person located at the project site / sites of displacement

Decision Making

   Decision making process involve consultation between the project proponent (assisted by a consultant) and the impact assessment authority (assisted by an expert group if necessary)

The decision on environmental clearance is arrived at through a number of steps including evaluation of EIA and EMP.

Monitoring the Clearance Conditions

 Monitoring should be done during both construction and operation phases of a project. This is not only to ensure that the commitments made are complied with but also to observe whether the predictions made in the EIA reports were correct or not.  Where the impacts exceed the predicted levels, corrective action should be taken. Monitoring will enable the regulatory agency to review the validity of predictions and the conditions of implementation of the Environmental Management Plan (EMP).

Components of EIA
Air Environment

    1. Determination of impact zone (through a screening model) and developing a monitoring network
    2. Monitoring the existing status of ambient air quality within the impacted region (7-10 km from the periphery) of the proposed project site
    3. Monitoring the site-specific meteorological data, viz. wind speed and direction, humidity, ambient temperature and environmental lapse rate
    4. Estimation of quantities of air emissions including fugitive emissions from the proposed project 
    5. Identification, quantification and evaluation of other potential emissions (including those of vehicular traffic) within the impact zone and estimation of cumulative of all the emissions/impacts
    6. Prediction of changes in the ambient air quality due to point, line and areas source emissions through appropriate air quality models
    7. Evaluation of the adequacy of the proposed pollution control devices to meet gaseous emission and ambient air quality standards
    8. Delineation of mitigation measures at source, path ways and receptor

Noise Environment
    
1. Monitoring the present status of noise levels within the impact zone, and prediction of future noise levels resulting from the proposed project and related activities including increase in vehicular movement.
2. Identification of impacts due to any anticipated rise in noise levels on the surrounding environment.
3. Recommendations on mitigation measures for noise pollution.


Water Environment
 1. Study of existing ground and surface water resources with respect to quantity and quality within the impact zone of the proposed project.
 2. Prediction of impacts on water resources due to the proposed water use / pumping on account of the project.
 3. Quantification and characterization of waste water including toxic organic, from the proposed activity.
4. Evaluation of the proposed pollution prevention and waste water treatment system and suggestions on modification, if required.
5. Prediction of impacts of effluent discharge on the quality of the receiving water body using appropriate mathematical / simulation models.
6. Assessment of the feasibility of water recycling and reuse and delineation of detailed plan in this regard.
     
Biological Environment

 Survey of flora and fauna clearly delineating season and duration.

1. Assessment of flora and fauna present within the impact zone of the project.
2. Assessment of potential damage to terrestrial and aquatic flora and fauna due to discharge of effluents and gaseous emissions from the project.
3. Assessment of damage to terrestrial flora and fauna due to air pollution, and land use and landscape changes. 
4. Assessment of damage to aquatic and marine flora and fauna (including commercial fishing) due to physical disturbances and alterations.
5. Prediction of biological stresses within the impact zone of the proposed project.
6. Delination of mitigation measures to prevent and / or reduce the damage.

Land Environment 

1. Studies on soil characteristics, existing land use and topography, landscape and drainage patterns within the impact zone.
2. Estimation of impacts of project on land use, landscape, topography, drainage and hydrology.
3. Identification of potential utility of treated effluent in land application and subsequent impacts.
4.Estimation and charaacterization of solid wastes and delineation of management options for minimization of water and environmentally compatible disposal.

Socio‑economic and Health Environment

1. Collection of demographic and related socio - economic data.
2. Collection of epidemiological data, including studies on prominent endemic diseases (e.g. fluorosis, malaria, fileria, malnutrition) and morbidity rates among the population within the impact zone.
3. Projection of anticipated changes in  the socio - economic and health due to the project and related activities including traffic congestion and delineation of measures to minimize adverse impacts.
4. Assessment of impact on significant historical, cultural and archeological sites / places in the area.
5. Assessment of economic benefits arising out the project.
6. Assessment of rehabilitation requirements with secial emphasis on scheduled area, if any.
s
Risk Assessment 
1. Hazard identification taking recourse to hazard indices, Inventory analysis, dam break probability, natural hazard probability etc.
2. Maximum credible accident (MCA) analysis to identify potential hazardous scenarios.
3. Consequence analysis of failures and accidents resulting in fire, explosions, hazardous releases and dam breaks etc.
4. Hazards and operability (HAZOP) studies.
5. Assessment of risk on the basis of the above evaluations.
6. Preparation of an on site and off site ( project effected area) Disaster management plan.

Environment Management Plan

   1. Delineation of mitigation measures including prevention and control for each environmental component and rehabilitation and resettlement plan.
    2. Delineation of monitoring scheme for compliance of conditions
    3. Delineation of implementation plan including scheduling and resource allocation

Roles in the EIA Process

EIA involves many parties, grouped by their role definition within the process. The following section outlines the basic responsibilities of various bodies:

    1. The Project Proponent
    2. The Environmental Consultants
    3. The Authority
    4. The Public
    5. The Impact Assessment Agency

The Role of the Project Proponent

The project proponent during the project planning stage decides the type of projects i.e. new establishment, expansion or modernisation. Later the project proponent needs to prepare the Detailed Project Report/Feasibility Report and submits the Executive Summary, which shall incorporate the project details, and findings of EIA study, which is to be made available to concerned public.

The proponent has to approach the concerned Authority for NOC and holding the public hearing. After the public hearing the proponent submits application to IAA for environmental clearance.

Role of Environment Consultant

Environmental consultant should be conversant with the existing legal and procedural requirements of obtaining environmental clearance for proposed project. The consultant should guide the proponent through initial screening of the project and establish whether EIA studies are required to be conducted and if so finalise the scope of such study. The consultant should also be fully equipped with required instruments and infrastructure for conducting EIA studies. The environmental consultant is responsible for supplying all the environment-related information required by the Authority and IAA through the proponent. The consultant is also required to justify the findings in the EIA and EMP during the meeting with the expert groups at IAA.


The Role of the Authority

 The Authority are responsible for assessing the compatibility of a proposed development with current operational and prescribed standards. If the development is in compliance, the authority will then issue its NOC. They shall also hold the public hearing as per the provisions of EIA notification. The details of public hearing shall be forwarded to IAA.

The Role of the Public
The public also has an important role to play in EIA. The concerned persons will be invited through press advertisement to review information and provide their views on the proposed development requiring environmental clearance.

The Role of the Impact Assessment Agency (IAA)
Where a proponent is required to obtain environmental clearance, the IAA will evaluate and assess the EIA report. In this process the project proponent will be given a chance to present his proposal. If a project is accepted the IAA will also prepare a set of recommendations and conditions for its implementation based on this assessment. Environmental clearance conditions and recommendations of IAA are made available to the public on request through Authority. During the implementation and operation of the project, the IAA will also be responsible for the environmental monitoring process.


                                                                 ................. Continued in EIA Part2........................