Environmental Impact Assessment(EIA)
- Key Elements of an Initial Project Description and Scoping
The key
environmental issues to be considered in relation to a projects characteristics
are discussed in Sectoral Guidelines published by MoEF from time to time. An
Initial Project Description (IPD) should at the very least provide the reviewer
with all the information necessary to enable project screening and scoping.
Specific
information that must be covered by the IPD includes:
- Location/current land use along with contours and whether it conforms to the development plans proposed for that area.
- Details of proposed project activity including the project cost.
- Outlining the key project elements during the pre-construction, the construction and the operation phases etc. as per the list of documents to be attached with the questionnaire
- The IPD may also include.
- Associated
activities
- Expected project
induced activities
- Project activities
as PERT chart and process as a flow chart delineating unit processes with
input-output.
The project proponent after suitable scoping should provide environmental information for
consideration in detailed EIA. The reviewer while assessing the report should focus on the crucial aspects
involving project location and characteristics.
Project Location(s)
The site(s) selection can be an effective approach
in minimising the requirement of mitigation measures. Proposed project locations
should be reviewed based upon regulatory and non-regulatory criteria. Project
siting restrictions depend on the sensitivity of the surrounding environment.
Sensitivity should be assessed in relation to proximity of the project to the places/sites listed in list of
identified ecologically sensitive zones (ESZ) notified by MOEF.
The siting
criteria delineated by MoEF include:
- As far as possible prime agricultural land/forest land may not be converted into an industrial site.
- Land acquired should be minimum but sufficient to provide for a green belt wherein the treated wastewater, if possible/suitable, could be utilised from wastewater treatment systems.
- Enough space may be provided for storing solid wastes. The space and the waste can be made available for possible reuse in future.
- Layout and form of the project must conform to the landscape of the area without unduly affecting the scenic features of that place.
- Associated township of the project if any to be created must provide for space for photo-graphic barrier between the project and the township and should take into account predominant wind direction.
In addition
the following distances should be maintained:
- Coastal Areas: at least 1/2 km from the high tide line (within 0.5 km of High Tide Line (HTL), specified activities as per CRZ notification, 1991 are permitted)(The HTL is to be delineated by the authorised agency only.)
- Estuaries: At least 200 metres from the estuary boundaries
- Flood Plains of the Riverine systems: at least 500 metres from flood plain or modified flood plain or by flood control systems
- Transport/Communication System: at least 500 metres from highway and railway
- Major Settlements (3,00,000 population) at least 25 km from the projected growth boundary of the settlement
In addition
to the siting criteria listed above, the proposed project location should be
reviewed in relation to the following
salient issues:
- Ambient air, water and noise quality standards
- Critically polluted areas
- Natural disaster prone areas
- Ecologically sensitive areas
- Availability of water and other critical infrastructures like electricity, roads with adequate width and capacity
Land Use
Impacts
When assessing the significance of potential land
use impacts, the reviewer will need to consider
the following:
- Total land coverage of the project
- Expected change in the landscape and topography
- Present and designated land use in conformity with regional developmental plans / master plan
- Dependent/resident population
- Assessed land capability/suitability in the region
- Assessed erosion potential in the region
- Unstable or critical hydrologic, biotic and abiotic components systems (especially drainage)
- Slope stability and proneness to land slide hazards
- Designated land use in the master plan/regional development plan
Consideration of Alternatives
Alternatives
must be considered with respect to the following:
- No project
- Siting of the project
- Technology/Processes
The reviewer
will need to evaluate whether or not the proposal has taken into consideration all feasible alternatives in
respect of siting, and the plant processes including mitigation methods.
No project:
Alternatives
of no project situation need to be weighed against the ecological implications.
Siting of
the project:
Specific
information that must be covered in site selection should include:
- Status of conformance with siting guidelines of MoEF
- Ambient environmental quality in the region and conformance
- Existence of sensitive receptors in the impact zone
- The characteristics of soil strata and potential for groundwater depletion/ contamination
- The location of the site in relation to the watershed, and suitability of the site vegetation and ecology
- Extent of resettlement and rehabilitation, including vulnerability of the affected populations
- Likely Stress on public utilities and services in the region
- Likely Stress on the ecosystem
Process
selection:
Criteria for
the process selection should include:
- Choices of inputs to generate minimal wastes and emissions causing minimum stress on resources
- Pollution prevention through maximising efficiency in the utilization of inputs
- Recycling and reuse of wastes and emissions
- Treatment of wastes and emissions
- Choice of appropriate mitigation methods to reduce the impacts
Construction Phase
Project
construction may require cutting, striping, levelling landscaping, topographic,
sea / riverbed or subsurface transformations, opening of new quarries
transportation of men and materials, construction of temporary houses any of
which can cause both positive and negative environmental impacts.
The
construction phase is especially significant in the case of infrastructure
projects. In such cases a detailed schedule of construction activities is
critical for scoping impacts. If the construction stretches over a prolonged
period (1-3 years), the impacts of habitat disturbances may be even more severe
in the construction phase than during operation phase. In addition, there may
be substantial influx of labour in some project areas that could create stress
on public utilities, services, public health and social relations.
Input
Requirements
A
pre-requisite to estimating the potential environmental impacts of a project is
the identification and recording of the
total project inputs including process technology, raw materials, water and energy.
While not
exhaustive, below is a checklist of the information likely to be
required for the scoping of project
inputs.
Information required:
Project Technology
- Available technology/equipment
- Cleaner options
Land
- Nature of land/soil
- Topography
Materials
- Physical and chemical nature of raw materials
- Source of raw material
- Storage
- Precautionary measures
- Mine discharge
- Top soil preservation and reuse
- Project output
Hazardous/Toxic materials management
1. Requirements of processing, transportation and
handling of any hazardous/toxic /flammable/explosive material(s)
2. Storage requirement for hazardous/toxic
flammable / explosive material(s)
3. Usage of any recycled, salvaged material from
industrial waste in the process.
Water
Water
requirement
- Average demand, peak demand at full production, source and type (treated/ untreated)
- Water drawal at intake vis-vis the requirement of competing user (If water supply is to be augmented from other source(s) for meeting both present and future requirements)
- Physico-Chemical characteristics of surface/ground water at the site and likely impact area
- Treatment requirements of water before use
- Physico-Chemical characteristics of treated water
Energy/Fuel
Total power
requirement for
- Existing facilities
- Proposed facilities
Sources of
power supply
- Public supply
- D.G.Set/Gas turbine
- Captive power plant
- Capacity, type of fuel, consumption
Details of
fuel used
- Coal
- Natural gas
- LSHS
- HSD
- Naphtha
- Furnace Oil
- Other (specify)
- Consumption (tonnes/day), Calorific Value (K Joules, kg), % Ash, % Sulphur, Source of supply, Mode of transportation to the plant site with justification and linkage details of technology for power generation
Transport
- Details of transport system to be used for transporting raw materials, finished products and wastes
Wastes
and Emissions
An
assessment of the significant environmental issues for each phase of the
project in relation to wastes and emissions involve
- Potential releases
- The receiving environment including bio-environment
The issues
that need to be identified are
- Air emissions
- Noise
- Liquid effluents
- Solid wastes
- Hazardous/Toxic Wastes
Types of release and potential sources.
A. Air Emissions
a.
Emissions from Compaction & setting during
construction
b.
Emissions from Drilling & blasting
c.
Emissions from Operation of DG. Sets/captive
power plant
d.
Vehicular emissions
e.
Emissions from storages & transport
f.
Process emissions
g.
Fugitive emissions
h.
Accidental /emergency releases
i.
Emissions from Fuel combustion
j.
Offsite emissions
B. Noise & Vibrations
a.
Generated by the plant and equipment
b.
From Vehicles
c.
Blast induced ground vibrations
C. Liquid Effluents
a.
Process and domestic effluents
b.
Offsite effluents
c.
Storm water
d.
Cooling tower effluents and boiler blow downs
e.
Effluents from treatment plant
f.
Effluents from emission mitigation system
g.
Acid Drainage
h.
Tailing Residue emplacement
i.
Ground / surface water contamination
j.
Accidental / emergency & spills
D. Solid
Waste
a.
Domestic solid waste
b.
Soil overburden/Dredged material/stripping and
quarrying waste
c.
Process/storage units sludge
d.
Sludge form ETP/STP
e.
Waste from emission mitigation system
f.
Accidental / emergency dumps
E. Hazardous
/ Toxic Waste
a.
Process / Storage units (tank bottoms)
b.
Sludge form Waste water treatment
c.
Sludge form Emission treatment system
d.
Leachates from storage
e.
Genetically modified organisms
f.
Biotechnological activities and related
emissions and wastes
Air Emissions
The issues for air emissions should be based on
project location (valley, coastal areas, regions with frequent dust storms etc.) type of
activity and air polluting potential. A list of key activities and associated air
pollutants are listed.
Liquid
Effluents
Detailed assessment will be required where:
- The proposed receiving body is surface water, irrigation canal, marine coast, public sewers etc.
- The discharge point is within the catchment area of a drinking water source or a river stretch designated for drinking purposes (as per CPCB designated usages)
- The disposal is on land, the soil is permeable and the aquifer conditions are prone to groundwater contamination
Solid
Wastes
Should the
proponent be unable to confirm the existence of an acceptable treatment or
disposal facility for any of the listed hazardous wastes classes with adequate
capacity the issue will need to form input into the detailed assessment. It is
important to note that in addition to those wastes that are classified, all
potential waste groups should be examined according to the following
parameters:
- Moisture and High Volatile matter
- Oil and Grease
- Calorific value
- pH
- Conductivity
- Heavy metal (Cr, Pb, Cu, Mn, Zn, Ni) concentrations
- Phenolic compound concentration
The comprehensive inventorization of solid wastes
is necessary, if
- The region has no land for disposal
- Existing capacity of the dumping site is near exhaustion
- The region has high intensity and/or duration of rainfall and the region is prone to flooding/water logging/high ground water table.
Risks to Environment and Human Health
Impacts to environment and human health can occur
from accidents (both on-site and off-site) or through general environmental degradation.
When determining the appropriate areas for a more detailed risk assessment, the reviewer should
take into account both the type of risks inherent in a particular activity and the potential for
human/ environment exposure.
Onsite
Exposure to
fugitive dust, noise, gases, thermal and other emissions
- House keeping practices requiring contact with solid and liquid toxic wastes
- Emission/spillage etc. from storage & handling
- Exposure to explosive material
- Exposure to toxic chemicals
Offsite
Exposure to
toxic releases from offsite / storage/related activities
- Contamination of ground / drinking water due to accidental releases or normal release in combination with natural hazard
- Deposition of toxic pollutants in vegetation / other sinks and possible sudden releases due to accidental occurrences
Socio-Economic Impacts
It is generally envisaged that the scale of a
projects socio-economic impact study is limited to the region and population directly influenced
by the project, with an emphasis on the distribution of benefits and costs
among the project stakeholders. Within project scoping, the socio-economic
issues should be addressed as below:
Socio-economic
- Onsite and offsite optimal land requirements, specifically in relation to the potential for displacement, rehabilitation, and habitat fragmentation
- Land acquisition details
- Quantity and nature of employment and /or estimated needs for migratory workers
- Potential for stress/ increase on utilities and services
- Potential benefits/disbenefits to the local habitants resulting through project and ancillary activities
- Impact on health of/due to migrant labour
- Impact on education of male/female
- Community health impacts
- Potential impacts on existing occupations and economic activities
- Potential losses of livelihood for local and vulnerable sections of the population
- Stress on medicinal plants
- Potential impacts to archaeological monuments and culturally/religiously important locations
Ecological Impacts
Project
proposals located nearby wildlife sanctuaries, National Parks, and/or biosphere
reserves, breeding /spawning /nesting
grounds etc need to come under careful scrutiny, and the EIA report should contain impact on such
ecologically fragile/sensitive areas.
Global Environmental Issues
India is a
signatory to many international agreements ratifying her commitment to environmental
concerns. Therefore global concerns must also be
considered. The reviewer will need to note whether a projects potential
resource consumption, waste generation and emissions could break international
codes of practice and where this is the case, the proponent should identify,
evaluate and suggest mitigation measures if any in the EIA report.
There are a
number of additional/optional areas, which may be considered:
- Potential trans. - boundary transport of atmospheric pollutants or liquid effluents.
- Potential impacts to wetlands of international importance and those that attract migratory birds
- The use or production of hazardous or toxic materials
- Potential impacts on primitive and rare cultivated plants, land, ethnic minorities, and archaeological places
- Impacts on identified rare and endangered species.
Emissions of nuclear radiation on-site and
off-site and potential for nuclear accidents
No comments:
Post a Comment